Global hydrogen industry reports $75 billion in committed capital but climate targets at stake due to project delays
BRUSSELS, Sept. 17, 2024 /PRNewswire/ — The global clean hydrogen project pipeline is growing and maturing, with a sharp increase in projects reaching final investment decision (FID), according to the Hydrogen Council’s latest analysis of more than 1,500 projects worldwide. At the same time, the pace and scale of deployment need to accelerate dramatically to meet global climate goals.
The Hydrogen Insights 2024 report, released today and co-authored by McKinsey & Company, reveals that while the global project pipeline has grown by a factor of seven since 2020 from 228 projects to 1,572 projects, as of May 2024, it has also matured, with a strong focus on advancing projects towards execution. Most notably, clean hydrogen projects that reached FID have also seen a seven-fold increase in committed investment, growing from approximately USD 10 billion across 102 projects in 2020 to some USD 75 billion across 434 projects in 2024.
The most recent data from October 2023 to May 2024 further underscores a clear shift from project planning to implementation. Total announced investments through 2030 have increased by approximately 20% – from USD 570 billion to USD 680 billion. The most notable growth has occurred in the more advanced stages of project development, with investments past FID growing by a remarkable 90%, followed by a 30% increase in front-end engineering design (FEED) stage projects.
This clear shift across the global project pipeline from announcements to implementation is coupled with natural attrition that fosters industry maturation by eliminating less viable projects and prioritising those with the highest potential, a pattern also seen in the early stages of other clean energy industries such as wind and solar.
Jaehoon Chang, President and CEO of Hyundai Motor Company and Co-Chair of the Hydrogen Council, said: “The seven-fold increase in committed capital for hydrogen projects reaching FID over the past four years demonstrates the industry’s progress. We are pleased to see the industry walking the talk at this critical transitional moment, as evidenced in the latest Insights report. Moreover, further action is needed to ensure an accessible and affordable hydrogen supply, enabling the widespread adoption of hydrogen.”
Despite progress, the hydrogen sector, like other clean energy industries currently, faces macroeconomic headwinds including rising inflation and interest rates, as well as geopolitical tensions affecting energy markets. Sector-specific issues such as regulatory uncertainty and increasing costs for renewable power and electrolysers have led to project delays, particularly for renewable hydrogen projects.
Ivana Jemelkova, CEO of the Hydrogen Council, said: “This report sends a clear message: hydrogen is happening. Now that hydrogen is a reality in the energy transition, it’s time to drive significantly more investment by 2030 to meet our mid-century targets. Equipped with concrete lessons learned from the past four years, we must urgently address challenges in key markets and create a more favourable environment for project execution.”
Sanjiv Lamba, CEO of Linde and Co-Chair of the Hydrogen Council, said: “Realising hydrogen’s full climate and socio-economic potential requires a united effort from governments and industry. With a supportive regulatory framework and targeted incentives, investors will have the certainty they need to move projects to FID – ultimately contributing to achieving global climate targets.”
About Hydrogen Insights
Hydrogen Insights is the Hydrogen Council’s regularly published perspective on the hydrogen industry’s evolution. It summarises the current state of the global hydrogen sector and actual hydrogen deployment. Authored by the Hydrogen Council in collaboration with McKinsey & Company, the report draws on a combination of public information and proprietary data from Hydrogen Council members and represents a collaborative effort to share an objective, holistic, and quantitative perspective on the status of the global hydrogen ecosystem.
About The Hydrogen Council
The Hydrogen Council is a global CEO-led initiative with a united vision and long-term ambition for hydrogen to accelerate the clean energy transition. It brings together a diverse group of 140 companies from 20 countries across Americas, Europe, Africa, the Middle East and Asia Pacific. Spanning the entire value chain, and including large multinationals, innovative start-ups as well as investors, the Council’s membership represents some $9 trillion in market capitalization, 6.8 million in FTEs and some $6.4 trillion in revenues.
The Council is committed to unlocking the sustainability potential of clean hydrogen, fostering business and technological innovation as drivers for sustainable growth, creating quality jobs and delivering social value. Using its global reach to promote collaboration between industry, governments, investors, and the civil society, the Council provides insights on and pathways for accelerating the deployment of hydrogen ecosystems around the world. It also supports the development of international safety and sustainability standards, paving the way for the deployment of reliable hydrogen solutions at scale.
To find out more visit www.hydrogencouncil.com and follow us on X @HydrogenCouncil and LinkedIn.
Media Enquiries
Joanna Damerell, Communications Manager, Hydrogen Council
[email protected]
Photo – https://mma.prnewswire.com/media/2507378/Hydrogen_Insights_2024_report.jpg
View original content:https://www.prnewswire.co.uk/news-releases/global-hydrogen-industry-reports-75-billion-in-committed-capital-but-climate-targets-at-stake-due-to-project-delays-302250196.html
Fintech PR
WorldSkills Lyon 2024: Talented Winners, Long-lasting Legacy
LYON, France, Sept. 19, 2024 /PRNewswire/ — After an intense week of competition, the 47th WorldSkills Competition has officially wrapped up, marking the end of a thrilling journey for 1,400 young professionals from around the globe. For four days, participants representing nearly 70 countries and regions competed fiercely in 59 diverse skill areas, transforming Lyon’s Eurexpo into a vibrant hub of craftsmanship and international talent.
From day one, the atmosphere was charged with energy as competitors showcased their expertise in sectors ranging from Manufacturing and Engineering to Fashion, Digital Technology, and Healthcare. The level of dedication and precision demonstrated throughout the week was a testament to the profound commitment these young professionals have to their trades, as well as their determination to showcase their nation’s worth on the global stage.
Last night, the closing ceremony of WorldSkills Lyon 2024, held at Groupama Stadium, brought the event to an emotional close with the announcement of medalists in each skill category. Four medals were awarded in each skill: Gold Medal, Silver Medal, Bronze Medal, and the Medallion for Excellence. This ceremony underscored the core belief of the WorldSkills movement: excellence is found in diversity – diversity of profiles, backgrounds, expertise, and techniques.
The list of medalists is now available. Visit https://worldskills.org/what/competitions/worldskills-lyon-2024/#results to discover the winners!
What’s next?
The impact of WorldSkills Lyon 2024 extends far beyond the event itself. As the competition unfolded, and millions of people followed it in person or through media, WorldSkills Lyon 2024 spotlighted the crucial role of vocational education in today’s world and in shaping our shared future. By celebrating excellence, the competition highlighted the incredible ability of youth to drive the change our world needs through their energy and dedication. The legacy of this event lies in every vocation it has sparked and every future career it has inspired. This 47th edition has once again shown the world that where there is skill, there is a way.
Media Contacts:
Alice Nahon
PR Officer
[email protected]
Anne-Laure TRONC
Press Relation Manager
[email protected]
Photo – https://mma.prnewswire.com/media/2510100/WorldSkills_Lyon_2024.jpg
Photo – https://mma.prnewswire.com/media/2510103/WorldSkills_Lyon_2024.jpg
Logo – https://mma.prnewswire.com/media/2205419/4921868/WordSkills_Lyon_Logo.jpg
View original content:https://www.prnewswire.co.uk/news-releases/worldskills-lyon-2024-talented-winners-long-lasting-legacy-302253405.html
Fintech PR
Touchless Vending Market Size to Grow USD 42330 Million by 2030 at a CAGR of 13.3% | Valuates Reports
BANGALORE, India, Sept. 19, 2024 /PRNewswire/ — Touchless Vending Market is Segmented by Type (Food and Beverage Vending Machines, Mask Vending Machine, Toy Vending Machine), by Application (Shopping Mall, Street, Hospital, Traffic Station): Global Opportunity Analysis and Industry Forecast, 2024-2030.
The Global Touchless Vending Market was valued at USD 19800 Million in 2023 and is anticipated to reach USD 42330 Million by 2030, witnessing a CAGR of 13.3% during the forecast period 2024-2030.
Get Free Sample: https://reports.valuates.com/request/sample/QYRE-Auto-12D11505/Global_Touchless_Vending_Market
Major Factors Driving the Growth of Touchless Vending Market:
The touchless vending machines market is seeing rapid growth, driven by rising demand for hygienic, contactless solutions post-pandemic, especially in public places such as shopping malls, traffic stations, and hospitals. The ability to offer convenience and reduce human interaction has made these machines popular in food and beverage, personal protective equipment (PPE), and even toy vending. Technological advancements in contactless payment systems and smart inventory management further boost adoption. However, high initial investment costs may slow market growth, especially in developing regions.
Buy Now: https://reports.valuates.com/api/directpaytoken?rcode=QYRE-Auto-12D11505&lic=single-user
TRENDS INFLUENCING THE GROWTH OF THE GLOBAL TOUCHLESS VENDING MARKET:
Food and beverage vending machines are highly popular in locations such as hospitals, shopping malls, and traffic stations, where consumers demand quick, hygienic access to snacks and drinks. These machines, equipped with touchless payment systems, Employee Background Check Software Market have seen increased adoption due to the convenience and enhanced hygiene they offer. In addition to traditional snacks and drinks, there is a growing trend toward healthier, premium food options in these vending machines, catering to health-conscious consumers, which further drives demand in this segment.
In shopping malls, vending machines are increasingly being used to provide convenience to shoppers, offering products ranging from snacks to toys and hygiene products. Touchless vending machines are particularly appealing due to their ability to cater to consumers who are looking for quick, contactless purchasing options while shopping. The presence of vending machines in high-traffic areas within malls ensures steady usage, and as malls look to enhance customer experiences, more advanced, interactive vending solutions are likely to be adopted.
Mask vending machines gained significant traction during the COVID-19 pandemic and continue to be relevant in hospitals, airports, and other high-traffic areas. These machines offer a convenient, touchless way for people to access face masks and personal protective equipment. While demand for masks has decreased slightly post-pandemic, the continued emphasis on public health and hygiene in high-risk locations ensures that these machines maintain a stable presence. Additionally, mask vending machines are being repurposed for other hygiene products, extending their utility.
Toy vending machines are commonly seen in shopping malls and entertainment centers, offering children and families a fun, convenient way to purchase toys. These machines are especially popular in high-traffic areas such as malls and family-friendly environments, where they offer an added entertainment element. Recent trends show a shift toward integrating digital elements, such as mobile apps and touchless payment options, into toy vending machines, enhancing the user experience and making these machines more interactive and appealing to younger audiences.
In hospitals, vending machines play a crucial role in providing essential items like snacks, beverages, and personal protective equipment (PPE), including masks. Touchless vending machines, in particular, have become more popular in healthcare environments due to their ability to reduce physical contact, thereby minimizing the risk of disease transmission. These machines are strategically placed in high-traffic areas, such as waiting rooms and cafeterias, ensuring that both staff and visitors have easy access to essential items without leaving the hospital premises.
Vending machines in traffic stations, including airports, bus terminals, and train stations, are seeing increased demand as more travelers seek convenient, contactless solutions for snacks and beverages during transit. Touchless vending machines are particularly favored in these locations due to their ability to offer quick, hygienic services to large numbers of travelers. With the growing number of people using public transportation, vending machines equipped with smart technology and contactless payment options are expected to become a staple in these locations.
Touchless vending machines are also becoming a common sight on streets and in other public spaces, providing convenience for passersby. These machines offer quick access to a variety of products, including food, beverages, and even hygiene items, such as masks and sanitizers. The convenience of contactless payment and minimal human interaction aligns well with the growing consumer preference for self-service, especially in outdoor environments. The installation of vending machines in streets and public spaces is expected to continue rising, driven by urbanization and consumer demand for 24/7 access to essential goods.
View Full Report: https://reports.valuates.com/market-reports/QYRE-Auto-12D11505/global-touchless-vending
TOUCHLESS VENDING MARKET SHARE
The Asia-Pacific region dominates the touchless vending machines market, driven by the high adoption rate of vending machines in countries like Japan and China, particularly in public spaces such as traffic stations and shopping malls. North America and Europe also show strong demand, especially for food and beverage vending machines in hospitals and other high-traffic areas. The Middle East and Africa are emerging markets, with increasing investments in smart city infrastructure and public health initiatives that support the adoption of touchless vending machines.
Key Companies:
- Digital Media Vending International LLC
- AusVendGroup
- AMS Group, Inc.
- LuxDisinfect
- Aeguana
- Vendekin
Purchase Chapters: https://reports.valuates.com/request/chaptercost/QYRE-Auto-12D11505/Global_Touchless_Vending_Market
SUBSCRIPTION
We have introduced a tailor-made subscription for our customers. Please leave a note in the Comment Section to know about our subscription plans.
DISCOVER MORE INSIGHTS: EXPLORE SIMILAR REPORTS!
– Contactless Touch Technology market was valued at USD 986.4 Million in 2023 and is anticipated to reach USD 1422.1 Million by 2030, witnessing a CAGR of 5.4% during the forecast period 2024-2030.
– AI-Powered Checkout market was valued at USD 217 Million in 2023 and is anticipated to reach USD 681.6 Million by 2030, witnessing a CAGR of 17.5% during the forecast period 2024-2030.
– Hospital Vending Machine Market
– Capsule-Toy Vending Machines market is projected to grow from USD 351 Million in 2024 to USD 635.8 Million by 2030, at a Compound Annual Growth Rate (CAGR) of 10.4% during the forecast period.
– The global Digital Process Automation market is projected to grow from USD 7215.7 Million in 2024 to USD 11770 Million by 2030, at a Compound Annual Growth Rate (CAGR) of 8.5% during the forecast period.
DISCOVER OUR VISION: VISIT ABOUT US!
Valuates offers in-depth market insights into various industries. Our extensive report repository is constantly updated to meet your changing industry analysis needs.
Our team of market analysts can help you select the best report covering your industry. We understand your niche region-specific requirements and that’s why we offer customization of reports. With our customization in place, you can request for any particular information from a report that meets your market analysis needs.
To achieve a consistent view of the market, data is gathered from various primary and secondary sources, at each step, data triangulation methodologies are applied to reduce deviance and find a consistent view of the market. Each sample we share contains a detailed research methodology employed to generate the report. Please also reach our sales team to get the complete list of our data sources.
YOUR FEEDBACK MATTERS: REACH OUT TO US!
Valuates Reports
[email protected]
For U.S. Toll-Free Call 1-(315)-215-3225
WhatsApp: +91-9945648335
Website: https://reports.valuates.com
Blog: https://valuatestrends.blogspot.com/
Pinterest: https://in.pinterest.com/valuatesreports/
Twitter: https://twitter.com/valuatesreports
Facebook: https://www.facebook.com/valuatesreports/
YouTube: https://www.youtube.com/@valuatesreports6753
https://www.facebook.com/valuateskorean
https://www.facebook.com/valuatesspanish
https://www.facebook.com/valuatesjapanese
https://valuatesreportspanish.blogspot.com/
https://valuateskorean.blogspot.com/
https://valuatesgerman.blogspot.com/
https://valuatesreportjapanese.blogspot.com/
Logo: https://mma.prnewswire.com/media/1082232/Valuates_Reports_Logo.jpg
View original content:https://www.prnewswire.co.uk/news-releases/touchless-vending-market-size-to-grow-usd-42330-million-by-2030-at-a-cagr-of-13-3–valuates-reports-302253401.html
Fintech PR
Savl Rebrands to Unity Wallet and Launches Loyalty Program, Boosting User Experience and Value
Known for its exclusive tools and unique features, Unity Wallet delivers the most comprehensive self-custodial crypto wallet and Web3 experience, for seamless and secure DeFi management.
LONDON, Sept. 19, 2024 /PRNewswire/ — Savl, the self-custodial crypto and Web3 wallet that combines industry-leading encryption, unique functionality, and intuitive design has rebranded to Unity Wallet, signifying a new era for the project.
With a mission to unlock DeFi’s potential for everyone, Unity Wallet promotes broader self-custody adoption through an intuitive, user-friendly design paired with industry-leading encryption and security.
Launched in 2020, Unity Wallet operates in over 100 countries and has generated more than 1 million wallets. Its innovative features set it apart, including a built-in social community, sub-accounts, staking, WalletConnect, encrypted messenger, and the unique Know Your Transaction (KYT) function, which allows users to assess risks on wallet addresses, protecting against fraudulent activities and ensuring a safer self-custodial crypto and Web3 wallet experience.
Further expanding its offerings, Unity Wallet now actively rewards its users through its recently launched loyalty program. Rewardable actions include buying, selling, swapping, sending, staking and socially engaging with other users. Points can then be used to progress through program tiers, reduce transaction fees, enjoy up to 50% cashback on cross-chain and DEX swaps, and be redeemed for additional sub-accounts, KYT checks, unique perks, and 24/7 dedicated support.
James Toledano, Chief Operating Officer of Unity Wallet, said, “Since its inception, our mission has been to simplify access to crypto. As the crypto landscape has evolved, so has Unity, leading to this rebrand and marking a pivotal point in our journey. Our new name reflects our commitment to providing a unified, accessible, and empowering user experience for all. The loyalty program is a key step towards this vision, designed not only to reward our community but also to drive the broader adoption of decentralized finance and enhance user experience and value.”
Unity Wallet can be downloaded via the Apple App and Google Play stores. For more information on the loyalty program visit https://www.unitywallet.com/loyalty-program.
About Unity Wallet
Unity Wallet is a self-custodial crypto and Web3 wallet that combines industry-leading encryption, unique functionality, and intuitive design. Launched in 2020 as a solution to the fragmented nature of existing wallets, Unity Wallet is a sleek alternative to complicated experiences. It operates across 100+ countries, with an impressive track record of 1,000,000 wallets generated. Its innovative features set it apart, including a built-in social community, encrypted messenger, and its unique Know Your Transaction (KYT) function, enabling users to conduct risk assessments on wallet addresses to safeguard against illicit activities. Unity Wallet safeguards user assets with a robust set of security measures, including a 24-word recovery phrase, anti-theft pin codes, and optional FaceID authentication, all powered by cutting-edge cryptographic algorithms and protocols. With its comprehensive suite of services, users can effortlessly engage in buying, selling, and storing over 250 cryptocurrencies, as well as cross-chain and DEX swapping across 100s of trading pairs, along with the ability to stake assets and create multiple sub-accounts for optimized asset management. Unity Wallet also facilitates the purchase of everyday products and services in over 190 countries using cryptocurrency, while its advanced WalletConnect integration grants access to the Web3 world and thousands of decentralized apps (DApps).
View original content:https://www.prnewswire.co.uk/news-releases/savl-rebrands-to-unity-wallet-and-launches-loyalty-program-boosting-user-experience-and-value-302253344.html
-
Fintech PR6 days ago
Medius Wins 2024 ISV Partner of the Year Award in Sweden
-
Fintech PR6 days ago
Magic Compass Group Launches New Brand and Prop Trading Business
-
Fintech PR6 days ago
ATFX Connect Launches NDFs
-
Fintech PR7 days ago
Elliott Criticizes the Republic of Korea’s Decision to Continue to Challenge the US $100 Million Arbitral Award at the Expense of Its Citizens
-
Fintech PR6 days ago
BingX Lists AgentLayer on Launchpool, Unlocking New Staking Opportunities
-
Fintech PR5 days ago
KuCoin Cares Extends up to 10,000 KCS Humanitarian Aid to Typhoon Yagi Victims in Vietnam
-
Fintech PR5 days ago
Response to possible offer announcement by ABC Technologies Inc. (“ABC Technologies”)
-
Fintech PR5 days ago
TIME, Statista Name Three SM companies Among World’s Best Companies